(CHANDLER, Ariz.) – The City of Chandler is moving ahead with plans to widen Kyrene Road from four lanes to six between Chandler Boulevard and the Loop 202 Santan Freeway. Project ST2503 aims to address peak-hour backups for commuters exiting the freeway. While still in the early design stage, construction is currently targeted for 2028. Public meetings are to be held before the final project design.
The segment of Kyrene Road is currently four lanes with two in each direction. The proposal would add a third lane in each direction to make it a six-lane stretch. Other possible improvements are in the works, including adding bus pads and improving medians, streetlights, landscaping, pedestrian facilities, and right-of-way acquisitions.
A ten-foot shared path for pedestrians and bikes has also been floated around. The project may also require utility relocations and will in part be funded by Proposition 479. The proposition was approved by voters in November 2024 and extended a 0.5% Maricopa County sales tax for 20 more years. The funds are to be used for regional transportation projects, such as freeways, street improvements, and public transit. Recent estimates put the total project cost at around $42 million.

Photo Credit: City of Chandler
According to the city, the project was initiated due to vehicles getting backed up on the Loop 202 while exiting onto Kyrene Road during rush hours. A project assessment in 2021 looked for options to help move traffic off the freeway and through the corridor to Chandler Boulevard. Transportation Planning Manager Jason Crampton agreed that two lanes in each direction are not sufficient for the traffic volume in the area.
While there have not been public comments about this project yet at Chandler City Council meetings, residents on Nextdoor offered mixed views. Priscilla Curley thinks Chandler “should only widen west side Kyrene, it is backed daily from 3 to 5,” noting that the east side does not back up. Richard Lloyd also mentioned that “the sight lines getting off of 202 onto Kyrene are unsafe. Maybe they can fix that too.”
Chandler recently performed road work improvements at Alma School Road and Pecos, including a double left-turn lane. The road work happened at the same time the new Costco Business Center at the intersection was being constructed, and finished as the retailer was opening up.
Resident Bryon Johnson commented that he hoped “that Costco had to pay for those improvements because the city spent millions improving Alma School a few years back.” Records show that Costco was responsible for specific public road improvements tied to their project.

Photo Credit: City of Chandler
The timeline has drawn criticism from some residents who feel the city is moving too slowly. The project design began in January 2026, with a traffic analysis being completed in April of the same year. Meetings are scheduled for late 2026 and into 2027. Right-of-way acquisition which includes some landscaped areas will be required before construction can start in 2028.
The city is asking for public feedback throughout the design process, and readers are encouraged to attend any meetings and utilize the public comment time.
The Kyrene widening project remains in design and no final plans have been approved as of yet. Chandler residents are encouraged to review materials and submit their comments through the city’s project page and at upcoming public meetings. Chandler has not released a detailed construction schedule or the final cost beyond its current estimates.
To add to or correct any information in this report, please contact me at george.y@lead4earth.org and leave a comment below with your thoughts on the proposed road construction in Chandler.